GarageBanner

City Hall Automated Garage and Community Plaza Project

Print

Interior LiftThe City of West Hollywood has awarded a contract to T.B. Penick & Sons, to construct the 200-car City Hall Automated Parking Garage and Community Plaza Project which will be located at 8300 Santa Monica Boulevard (City Hall).

 New!
 
Construction Webcam
Camera refreshes every 60 seconds.
 construction progress
View construction progress photos!
We'll be adding photos to this Flickr set periodically.

 

Automated parking garages can hold as many as three times the number of cars as traditional ramp-style parking garages. Operationally, automated parking garages provide customers with a valet-like parking experience that is fast, safe, and convenient. They are also less expensive to build when compared to conventional parking garages. Automated parking garages utilize computer-controlled motorized lifts, conveyors and shuttles to transport cars from the arrival level to a parking space and vice versa, without human assistance.

The City selected LPA, Inc. to design the Automated Parking Garage and Community Plaza Project. Don Monahan of Walker Parking Consultants, Inc. provided analysis and technical expertise. Unitronics designed the automated vehicle storage and retrieval system for the garage. Renowned artist Ned Kahn will provide the public art component of the project.

 

Construction Update    

  • March 30, 2015 (Monday)
    • Although City Hall is closed in honor of Cesar Chavez Day, it is not a typical holiday observed by the construction trades and the contractor is allowed to work.
    • The contractor continues to install underground utilities between the new parking garage and the existing City Hall building all week.
    • The contractor continues to install the aluminum curtain wall all week.
    • The contractor continues to paint the structure for the photovoltaic panels and the guardrails.
    • On the interior the contractor will be washing & sealing concrete floors on the 3rd level.

  • March 31, 2015 (Tuesday)
    • The contractor continues to install the aluminum curtain wall all week.
    • The contractor continues to paint the structure for the photovoltaic panels and the guardrails.
    • The contractor continues to install underground utilities between the new parking garage and the existing City Hall building all week.
    • On the interior the contractor will be washing & sealing concrete floors on the 3rd level.

  • April 1, 2015 (Wednesday)
    • The contractor continues to paint the structure for the photovoltaic panels and the guardrails.
    • The contractor continues to install underground utilities between the new parking garage and the existing City Hall building all week.
    • The contractor continues to install the aluminum curtain wall all week.
    • On the interior the contractor will be washing & sealing concrete floors on the 2nd & 3rd level.

  • April 2, 2015 (Thursday)
    • The contractor continues to install underground utilities between the new parking garage and the existing City Hall building all week.
    • The contractor continues to install the aluminum curtain wall all week.
    • On the interior the contractor will be washing & sealing concrete floors on the 2nd level.

  • April 3, 2015 (Friday)
    • The contractor continues to install underground utilities between the new parking garage and the existing City Hall building all week.
    • The contractor continues to install the aluminum curtain wall all week.
    • On the interior the contractor will be washing & sealing concrete floors on the 1st & 2nd level.

 

Sweetzer Permit (SP) Parking

On May 13, 2014 the City held a neighborhood meeting that was noticed to the 900 & 1000 blocks of Sweetzer Avenue. The purpose of the meeting was to identify potential options to address temporary construction mitigation for the automated parking garage behind City Hall. Those in attendance at the meeting urged the City to implement interim preferential parking regulations on Sweetzer Avenue throughout the construction period. In order to measure public support on the issue for those residents that did not attend the meeting, a survey was mailed to Sweetzer Avenue residents between Santa Monica Blvd and Willoughby Avenue. The survey asked residents if they supported the preferential parking plan as a construction mitigation measure that would end upon completion of the automated garage construction, unless a formal petition representing a majority of the residential dwelling units was submitted to the City Council for consideration. 93% of the survey responses the City received were in favor of implementing the recommendation that came from the neighborhood meeting.

Parking signs are in place that restricts parking to only Sweetzer Avenue permit holders between 7 p.m. and 8 a.m. every day. Enforcement of the new regulations began on September 9, 2014.

Vehicles displaying the specially designated Sweetzer Avenue parking passes (SP), available only to residents with Sweetzer Avenue addresses, are required. District 9 parking passes will not be honored on Sweetzer Avenue, however Sweetzer Avenue passes may be used on adjacent streets in District 9. Sweetzer Ave residents who live in the 900 and 1000 block, have been sent instructions to obtain complementary parking passes.


Informational Video

email icon  Sign up to receive an email notification when important updates are made on this Capital Project.