GarageBanner

City Hall Automated Garage and Community Plaza Project

Interior LiftThe City of West Hollywood has awarded a contract to T.B. Penick & Sons, to construct the 200-car City Hall Automated Parking Garage and Community Plaza Project which will be located at 8300 Santa Monica Boulevard (City Hall).

 New!
 
Construction Webcam
Camera refreshes every 60 seconds.
 construction progress
View construction progress photos!
We'll be adding photos to this Flickr set periodically.

 

Automated parking garages can hold as many as three times the number of cars as traditional ramp-style parking garages. Operationally, automated parking garages provide customers with a valet-like parking experience that is fast, safe, and convenient. They are also less expensive to build when compared to conventional parking garages. Automated parking garages utilize computer-controlled motorized lifts, conveyors and shuttles to transport cars from the arrival level to a parking space and vice versa, without human assistance.

The City selected LPA, Inc. to design the Automated Parking Garage and Community Plaza Project. Don Monahan of Walker Parking Consultants, Inc. provided analysis and technical expertise. Unitronics designed the automated vehicle storage and retrieval system for the garage. Renowned artist Ned Kahn will provide the public art component of the project.

Construction Update    

What to Expect:

  • September 22, 2014 (Monday)
    • Concrete Pour T.B. Penick & Sons rescheduled their concrete pour that was expected to be done last week Friday to today. Concrete will be poured for the shuttle way on the 3rd floor. They anticipate approximately 8-10 concrete trucks will be coming to the job site throughout the day.
    • T.B. Penick & Sons will continue to set the forms and install the rebar for the 3rd floor deck slab.
  • September 23, 2014 (Tuesday)
    • T.B. Penick & Sons will continue to set the forms for the 3rd floor deck slab. T.B. Penick & Sons expects delivery of large rails today. Expect a temporary lane closure/traffic control while the rails are taken off a large truck.
    • Various trades will be on-site to install their conduits into the 3rd floor deck slab.
  • September 24, 2014 (Wednesday)
    • T.B. Penick & Sons will continue to install conduits and rebar for the 3rd floor deck. They will also start installing the rails for the 3rd floor shuttle way.
  • September 25, 2014 (Thursday)
    • T.B. Penick & Sons expects to complete the reinforcing for the 3rd floor deck in preparation for the next concrete pour.
  • September 26, 2014 (Friday)
    • Concrete Pour T.B. Penick & Sons anticipates there will be the second large concrete pour for the third floor deck. Concrete will be poured for the shuttle way on the 3rd floor. They anticipate approximately 30 concrete trucks will be coming to the job site throughout the day. This will have to be a continuous concrete pour for 13 hours, and once they start they cannot stop. Expect temporary traffic control as concrete trucks are going into and out of the jobsite. Avoid the area or use alternate routes if possible.

Sweetzer Permit (SP) Parking

On May 13, 2014 the City held a neighborhood meeting that was noticed to the 900 & 1000 blocks of Sweetzer Avenue. The purpose of the meeting was to identify potential options to address temporary construction mitigation for the automated parking garage behind City Hall. Those in attendance at the meeting urged the City to implement interim preferential parking regulations on Sweetzer Avenue throughout the construction period. In order to measure public support on the issue for those residents that did not attend the meeting, a survey was mailed to Sweetzer Avenue residents between Santa Monica Blvd and Willoughby Avenue. The survey asked residents if they supported the preferential parking plan as a construction mitigation measure that would end upon completion of the garage, unless a formal petition representing a majority of the residential dwelling units was submitted to the City Council for consideration. 93% of the survey responses the City received were in favor of implementing the recommendation that came from the neighborhood meeting.

New parking signs are in place that restricts parking to only Sweetzer Avenue permit holders between 7 p.m. and 8 a.m. every day. Parking Enforcement officers began issuing warnings on August 26, 2014. Warnings will only be placed on vehicles that do not display a Sweetzer Permit until enforcement of the new regulations begins 7:00 p.m. on September 9, 2014.

Vehicles displaying the specially designated Sweetzer Avenue parking passes (SP), available only to residents with Sweetzer Avenue addresses, are required. District 9 parking passes will not be honored on Sweetzer Avenue, however Sweetzer Avenue passes may be used on adjacent streets in District 9. Sweetzer residents have been sent instructions to obtain complementary parking passes before enforcement of the new regulations begins 7 p.m. on September 9, 2014.

Informational Video

email icon  Sign up to receive an email notification when important updates are made on this Capital Project.